RA bill format explained

A running account bill is a part bill for work done so far on a contract. Its layout lets the client’s engineer check only what is new.

The columns

ColumnWhat it means
Item, description, unit, rateFrom the BOQ (bill of quantities) in the work order.
BOQ quantityThe quantity agreed in the contract.
PreviousQuantity already billed in earlier RA bills.
This billQuantity measured since the last bill.
Up to datePrevious + this bill.
AmountsThe same three columns multiplied by the rate.

The client pays for the This bill amount. Up-to-date columns let them check that the total so far stays within the BOQ.

A worked example (RA bill No. 3)

ItemRatePreviousThis billUp to dateThis bill ₹
PCC 1:4:8 (Cum)5,20040105052,000
Brick work (Cum)6,8002515401,02,000

Value of work this bill ₹1,54,000. GST 18% ₹27,720 (₹13,860 CGST + ₹13,860 SGST). Bill amount ₹1,81,720. Less retention 5% ₹7,700 and income-tax TDS 2% ₹3,080 (both on ₹1,54,000). Net payable ₹1,70,940. (Example only.)